Financing the Retrofit

Lenders, building owners, municipalities, appraisers, insurers and builders met in Winnipeg to test three retrofit financing models against Manitoba’s realities. Here’s what we heard, and where it goes next.

Deep energy retrofits pay off over decades, but the money has to be found up front. That gap is one of the biggest reasons Manitoba’s existing buildings aren’t being upgraded faster.

On October 27th, Sustainable Building Manitoba, BizforClimate and Manitoba Eco-Network brought together people who see the retrofit process from every angle: lenders, property owners and operators, municipal representatives, appraisers, insurers and builders. Their experience helps show how retrofit financing could work in Manitoba and where it is likely to get stuck. The goal was practical. Participants spent the morning pressure-testing three financing models against how Manitoba’s building sector actually works:

  • PACE (Property Assessed Clean Energy): retrofit costs repaid through the property tax bill, with the obligation staying with the building rather than the owner.
  • Green Banks: public or mission-driven lenders that use public capital to draw in private investment for projects conventional lenders won’t yet take on.
  • Energy-as-a-Service (EaaS): a provider funds, installs and maintains the upgrades, and the building pays back from the energy savings, with no upfront capital from the owner.

The Honourable Mike Moyes, Manitoba’s Minister of Environment and Climate Change, joined the session and spoke to the provincial government’s commitment to advancing energy retrofits across the province.

What we heard

The room largely agreed on the diagnosis. Cost is the barrier people name first, a credible business case matters more than anything else, and no single financing tool will do the job alone. Live polling during the session put numbers to that.

Who was in the room

Around 40 people took part in the polling. Non-profit and civil society made up the largest group (22%), followed by financial institutions and lenders (14%). Builders and trades, provincial and federal government, and utilities or efficiency organizations each made up 11%. Municipal staff, project developers, property owners and appraisers rounded out the room.

Participants came in fairly well informed, rating their awareness of deep energy retrofits 3.8 out of 5. By the end of the morning, that rose to 4.3.

Cost is the first answer, but projects stall before financing

Asked to name the biggest barrier in a word or two, 13 of 40 people said simply “cost.” Most other answers were variations on money, capital and financing, followed by awareness and education.

The research presented that day pointed to an earlier stage in the process. Most projects stall before financing is even on the table, at the advice, business-case and verified-savings stages. Participants said that matched their experience (3.7 out of 5). When asked to rank what matters most, they put a credible business case with verified savings first, ahead of long-term affordable financing, skilled trades capacity, and clear rules.

Built for the grid, the bill and emissions

Asked what Manitoba’s retrofit financing should be designed around first, the most common answer was grid capacity relief for Manitoba Hydro (13 of 44). Lower, more predictable energy bills (10) and emissions reductions (10) followed close behind. That’s a distinctly Manitoban answer. With clean, low-cost hydro power, the case for retrofits rests on freeing up capacity as much as on cutting carbon or bills.

Strong agreement on a coordinated mix

StatementAverage agreement (1–5)
No single financing tool will scale deep retrofits on its own. Manitoba needs a coordinated mix.4.7
Private lenders will invest more in retrofits if the government shares some of the risk.4.1
Timing retrofits with planned equipment or building renewal is key to making them affordable.4.1
With Manitoba’s low energy rates, most deep retrofits will need some public financial support.3.8
Manitoba is ready to launch a pilot within the next 12 to 18 months.3.4

The need for a mix of tools drew near-unanimous agreement. Readiness for a near-term pilot drew the least, which suggests real appetite but open questions about whether the groundwork is in place.

Who should lead, and where government should start

Asked who is best placed to coordinate and deliver retrofit financing, 63% chose a partnership of several players rather than any one institution. An expanded Efficiency Manitoba came next at 26%. A new green bank or green credit union drew 6%, and no one picked private lenders on their own.

On where the province should focus, participants ranked setting the rules (enabling legislation and standards) first, then funding project development (advice, business cases, bundling projects), then rewarding verified results. Cheaper borrowing and risk-sharing with lenders came last. That’s a notable tension: participants agreed risk-sharing would bring in private lenders (4.1), yet ranked it as the government’s lowest priority. Getting projects ready comes before financing them.

The one-word message for government was clear. “Action” and “start” topped the list, followed by collaboration, integration and “listen to the industry.”

From the room to the report

What participants shared will directly shape our upcoming report and the recommendations we bring to policymakers.

The report will build in three ways:

  1. Grounding each model in Manitoba’s context. Rather than describing PACE, Green Banks, and EaaS in the abstract, the report will set out where each fits within the province’s building stock, ownership patterns, and existing programs.
  2. Naming the barriers, and who can remove them. The hurdles raised by lenders, appraisers, insurers, municipalities and builders will be matched to the level of government or industry partner best placed to address them.
  3. Practical recommendations. The aim is a short list of concrete steps that would unlock more deep retrofits in Manitoba, tested against the experience of the people who would have to make them work.

The momentum is there to build on. Most participants plan to follow up with people they met (16 of 35), stay informed (15) or share the findings in their organization (13). Several want to join a working group (5) or explore a pilot in their own buildings (4). We expect to share the final report in early 2027.

Financing the Retrofit was hosted by Sustainable Building Manitoba, BizforClimate and Manitoba Eco-Network, and delivered under Natural Resources Canada’s Deep Retrofit Accelerator Initiative.

More Resources

Manitoba Tourism Climate Toolkit

Climate change is already a business risk for Manitoba tourism. Operators who plan for disruptions will keep guests, staff and revenue when others lose a season. In 2025, wildfires closed Whiteshell Provincial Park over the May long weekend, the traditional start of the season. [1] By June, about 21,000 people …

You Are What You Leave Behind

How Richard Rosin built a greener, more humane business with a kazoo, human intuition, and by trusting our oldest traditions. It replaces anxious thoughts with a series of products and a theatrical experience directed by strangers. People of appearances, we pay to make death look like life, but in reality, …

RRC Polytech reaffirms its commitment to sustainability through BizforClimate Pledge

Pictured above (L-R): Stephanie Fulford, Manager of Sustainability and Climate Strategy, RRC Polytech and Derek Earl, Founder, BizforClimate. RRC Polytech has joined more than 270 Manitoba organizations in signing BizforClimate’s Climate Action Pledge. The pledge reflects RRC Polytech’s commitment to climate action across the institution, from operations and facilities to …

Manitoba just put its climate cards on the table

The Manitoba government has released its long-awaited Net Zero Action Plan: 10 priorities, 42 initiatives, 90 actions, spanning everything from energy and buildings to transportation and industry. It can rightly be described as a whole-of-government effort, and just as important, it treats climate and economic development as the same project …

BizforClimate: Turning Climate Ambition Into Business Action

A few years ago, we kept hearing the same thing from Manitoba business leaders: “We are concerned about climate change, and recognize the growing risks, but we don’t know where to start.” Some felt overwhelmed. Others worried about cost. Many were already doing good work but weren’t sure how to …